The Energy Miser

The True Timeline to Get Solar Installed in New England

Why It’s Worth the Wait for Clean, Affordable Power 

Installing solar panels on your home is a lot like remodeling your kitchen. There’s careful planning, permits to secure, and coordinated work between professionals. While it may take time, the payoff—clean, affordable energy for decades—is well worth it. 

At New England Clean Energy, transparency is a top priority. We make sure every customer understands exactly what to expect throughout the process, with no surprises. From contract to connection, the full timeline typically takes 3 to 4 months, and we’ll keep you updated at every step. 

Step 1: Getting Started (1–2 Weeks) 

Your solar journey begins with a conversation. We’ll meet with you to understand your energy goals, review your property, and walk you through financing options. After a site visit to assess your roof and electrical system, you’ll receive a proposal. Once you sign the contract, we’re off and running. 

Step 2: Custom Design & Engineering (30–45 Days) 

Next, our team creates a custom solar system tailored to your home or business. This design phase includes technical analysis to ensure optimal performance, efficiency, and safety. We’ll also prepare and submit plans for town approval, making sure your system complies with all local building codes. 

Step 3: Permitting & Approvals (30–40 Days) 

Here’s where we hit the pause button—but only briefly. Before installation, we need to secure all required town permits and utility approvals. Timing can vary depending on your town, but rest assured: we handle all the paperwork and logistics. During this time, we’ll also order your system components and tentatively schedule your installation.

Step 4: Installation (1–3 Days) 

With permits in hand and materials on-site, our expert installers will bring your solar system to life. Most residential systems take just one or two days to install, though larger or more complex systems may take slightly longer. Our crews are efficient, professional, and leave your property spotless. 

Step 5: Inspection & Utility Approval (15–30 Days) 

We’re almost there! After installation, we schedule a final inspection and apply for a Certificate of Completion. The last step is receiving Permission to Operate (PTO) from your utility company. This final stretch can take a few weeks, but once approved, your system is ready to start producing clean energy. 

Why Starting Now Pays Off 

We get it—waiting isn’t fun. But working with a local installer who understands New England’s permitting and utility processes can make a big difference. And while you’re waiting, remember: the fuel for solar is free, and the sooner you go solar, the sooner you’ll start saving. With electricity rates only going up, now is the time to invest in the most cost-effective way to power your home. 

Ready to take the first step?

Call us at 877-886-8867 or schedule your free consultation today: https://newenglandcleanenergy.com/get-a-quote/ 

 

If you liked this article, you may also like:

Energy Independence: Why It Matters Now — And How Solar Can Help You Take Control

5 Reasons to Go Solar No Matter the Season

Four Things You Can Do To Save Solar

 

Exit mobile version